TANK TERMINALS · TANK FOUNDATIONS
Brine Storage Tank Ring Foundations
United Brine Services · Clemville, TX · Brine Storage Terminal ✓ 0 RECORDABLES
Finished terminal: nine brine storage tanks on Mirage ring foundations
Tank ring foundations (66′ & 77′)
Structural concrete
Grade 60 rebar
Completed
Project Overview
Mirage self-performed the complete foundation package for United Brine Services’ storage tank expansion in Clemville. The job was nine reinforced concrete ring wall foundations: six 66′ tanks and three 77′ tanks. Each foundation is a 1′ × 5′ ring beam centered on the tank shell, reinforced with sixteen #6 continuous horizontal bars on each face and #4 verticals at 24″, with a 6″ × 24″ concrete seal slab. Inside the rings, Mirage placed the granular base and approximately 33,500 SF of 2″ asphalt tank pad. The project was completed in 12 weeks.
Scope of Work
Self-performed: Excavation and subgrade prep · Formwork · Rebar fabrication and placement · Concrete ring beams and seal slab · Granular base · Asphalt tank pads · Backfill
Results
Nine complete tank foundations turned over ready for tank erection in 12 weeks, with zero recordable incidents.
Planning a tank or terminal project?
Serving the Texas Gulf Coast, from Brownsville to Beaumont.