TRAFIGURA FIELD SERVICES
Capability: Mechanical
Owner: Trafigura AG
Project: George West Terminal
Engineer: Govind Development
General Contractor: Trafigura
Project Type: $1,387,962.00
roject Description
Mirage was contracted by Trafigura to install piping and their new George West terminal and perform tie in to ETC line coming through site.
Work Performed
- Fabricated and installed 4,870 L.F. pipe
- Set 3 mechanical pumps
- Fabricated and installed firewater loop, fire water monitor, and firewater pump.
Accomplishment
Effectively completed project with no OSHA recordable incidents or lost time accidents.
Challenges
Working with several other on-site contractors with limited space and limited resources.